# GoChat Rolling Upgrade Strategy # Reference: Chatwoot deployment uses zero-downtime upgrade pattern ## Overview GoChat follows a blue-green deployment strategy for production upgrades, ensuring zero downtime during version transitions. ## Upgrade Process ### Step 1: Pre-flight Checks 1. Verify new Docker image is built and pushed: `docker pull gochat/gochat:${NEW_VERSION}` 2. Run database migrations on a staging environment first 3. Verify backward compatibility of migrations (new code must work with old schema) 4. Check feature flags — new features should be disabled by default ### Step 2: Database Migration ```bash # Run migrations BEFORE deploying new code # Migrations must be backward-compatible docker compose -f docker-compose.prod.yml exec gochat /app/gochat migrate up ``` ### Step 3: Blue-Green Deployment (Docker Compose) ```bash # 1. Deploy new version as "green" alongside "blue" (current) docker compose -f docker-compose.prod.yml up -d --no-deps gochat-green # 2. Wait for health check to pass curl -f http://gochat-green:3000/health # 3. Switch traffic (update nginx/upstream config) # nginx: switch upstream from blue to green # 4. Drain old connections on blue # Wait 30s for in-flight requests to complete # 5. Stop blue docker compose -f docker-compose.prod.yml stop gochat ``` ### Step 4: Verification 1. Smoke test: hit /health endpoint 2. Check logs for errors: `docker compose logs gochat --since 5m` 3. Verify metrics: Prometheus dashboard should show normal traffic 4. Monitor for 15 minutes before finalizing ### Step 5: Rollback (if needed) ```bash # Docker Compose rollback docker compose -f docker-compose.prod.yml exec gochat /app/gochat migrate down ${N} docker compose -f docker-compose.prod.yml up -d --no-deps gochat-${OLD_VERSION} ``` ## Migration Compatibility Rules - Migrations MUST be additive only in production (add columns, never remove) - Column removals require a 2-phase migration: soft-remove then hard-remove - New columns should have defaults or be nullable - Renames require a 3-phase migration: add new → copy data → remove old ## Worker Upgrade Workers drain naturally: set a shutdown deadline, let in-flight jobs finish, then stop. New workers pick up queued jobs from Redis.